Unique Installation | |||
---|---|---|---|
Details | FRL | Specimen # | Report No. |
Acoustic Lagging on Pipes | |||
Up to 100mm PVC stack lagged in Soundlag 4525C or Thermotec NuWrap 5 to base of cast-in collar | -/120/120 | Section 3.3, e. | FCO3426 |
Up to 100mm PVC floorwaste lagged in Soundlag 4525C or Thermotec NuWrap 5 to base of cast-in collar | -/120/120 | Section 3.3, e. | FCO3426 |
Up to 160mm HDPE stack lagged in Soundlag 4525C or Thermotec NuWrap 5 to base of cast-in collar | -/120/120 | Section 3.3, f. | FCO3426 |
50mm HDPE floorwaste lagged in Soundlag 4525C or Thermotec NuWrap 5 to base of cast-in collar | -/120/120 | Section 3.3, Table 17a | FCO3426 |
150mm PVC floorwaste through a H150FWS completely lagged to the base of the collar in Soundlag 4525C | -/240/180 | 5 | FSP2264 |
100mm PVC 4-way riser floorwaste through a H100FWS completely lagged to the base of the collar in Soundlag 4525C | -/120/120 | 5 | FSP2028 |
100mm PVC floorwaste through a H100FWS completely lagged to the base of the collar in Thermotec NuWrap 5 | -/240/240 | 2 | FR5670 †† |
50mm PVC floorwaste through a H50FWS completely lagged to the base of the collar in Thermotec NuWrap 5 | -/240/240 | 3 | FR5670 †† |
150mm PVC stack through a H150S completely lagged to the base of the collar in Soundlag 4525C | -/240/180 | 1 | FSP2264 |
Beer Python (Beverage Python | |||
130mm thick beer python (12 x 12mm & 8 x 16mm tubes) with 25mm thick foam insulation through 150mm concrete slab and HP150R | -/180/180 | 3 | FSP2298 |
Collars in a Cluster | |||
Up to 160mm stack cast-in collars in a 2x10 cluster | -/120/120 | Section 3.3, b. | FCO3426 |
20 x H110S in a 2x10 cluster | -/120/120 | FCO3373 | |
2 x H100S, H150S & a H50S in a cluster | -/240/120 | 1 | FSP1741 |
Collars in the Side of a Beam | |||
Up to 160mm plastic pipe services, stack or floorwaste, exiting the side of a beam through a cast-in collar | -/120/120 | Section 3.2, f., ii. | FCO3426 |
H150S cast-in the side of a concrete beam protecting a 150 PVC stack | -/240/240 | C | FRT190069 |
H100S cast-in the side of a concrete beam protecting a 100 PVC stack | -/240/240 | 1 | FSP1715 † |
L100FWS cast-in the side of a concrete beam protecting a 100 PVC floorwaste | -/240/240 | 2 | FSP1715 † |
L50S cast-in the side of a concrete beam protecting a 50 PVC stack | -/240/240 | A | FRT190069 |
Collar Recessed into the Slab | |||
Cast-in collar systems recessed 35mm into a slab | -/120/120 | Section 3.3, d. | FCO3426 |
H100FWS recessed 50mm into the slab protecting a 100 PVC floorwaste | -/240/240 | 22 | FR5670 †† |
Floorwaste Retrofit Under Stack Cast-in | |||
100mm PVC floorwaste with H100S cast-in a 150mm concrete slab with a LP100R mounted underneath | -/240/240 | 4 | FSP1673 † |
50mm PVC floorwaste with H50S cast-in a 150mm concrete slab with a LP50R mounted underneath | -/240/240 | 3 | FSP1673 † |
100 PVC floorwaste and 100 green under LP100R-D | -/240/180 | 1 | FSP2271 |
Fuseal PP110 Pipe Installations | |||
110 Fuseal Floor Waste in a 180mm+ concrete slab through H100FWS w/ LP100R-D underneath | -/240/240 | 1 | FSP2274 |
Gerberit SuperTube and SoVent | |||
SuperTube BottomTurn Bend pushed all the way up into a 110R | -/240/180 | 5 | FSP2116 |
SuperTube BottomTurn Bend pushed all the way up into a H100S | -/240/180 | 4 | FSP2116 |
SuperTube and Sovent Fitting used anywhere in the HP100R, 110R, H100S, L100FWS, H110S & H150S | -/240/180 | FCO3396 | |
HDPE Butt Welds | |||
HDPE butt welds to be located anywhere within the HP100R, 110R, H100S, L100FWS, H110S & H150S | -/240/180 | FCO3396 | |
Non-Fire Rated Sealant | |||
H100S-RR with 20mm bead of non-fire rated, neutral cure Roof and Gutter Silicone Sealant around pipe | -/240/240 | 3 | FSP1830 |
Paint on Collars | |||
Base flange of cast-in collars (Up to 150 size) coated in paint | -/120/120 | Section 3.2, e., iii. | FCO3426 |
Up to 150mm PVC stack with a thin sprayed layer of Taubmans Easycoat ceiling white paint or Taubmans ceiling premium white paint on collar shell and intumescent | -/120/120 | Section 3.3, e. | FCO3426 |
PEX Pipe Bundles | |||
Bundle of 3 x 25mm PEX-b pipes through an H50FWS cast-in collar | -/120/120 | 2 | FSP1872 |
Bundle of 4 x 20mm PEX-b pipes through an H50FWS cast-in collar | -/120/120 | 3 | FSP1872 |
Bundle of 3 x 20mm PEX-a pipes through an LP50R collar under a concrete slab | -/240/240 | 2 | FSP1849 |
Bundle of 2 x 20mm PEX-b pipes through an 32R collar on a 2x13mm plasterboard wall | -/120/120 | 6 | FSP1902 |
Bundle of 20mm PEX-b pipe & 20mm PEX-Al-PEX pipe through an 32R collar on a 2x13mm plasterboard wall | -/120/120 | 9 | FSP1902 |
Bundle of 20mm PEX-b pipe & 25mm PEX-Al-PEX pipe through an 50R collar on a 2x13mm plasterboard wall | -/120/120 | 4 | FSP1902 |
Unused Collars | |||
50 to 100 cast-in collars blanked off with a PVC plug | -/240/120 | Section 3.2, d., ii. | FCO3426 |
50 to 150 cast-in collara blanked off with GAL plate and filled with concrete (Installation Instructions) | -/240/240 | Section 3.2, d., i. | FCO3426 |
H150S blanked off with 150mm PVC plug | -/240/180 | 2 | FSP2271 |
H100FWS blanked off with GAL plate and filled with concrete (Installation Instructions) | -/240/240 | 20 | FR5670 †† |
H110S blanked off with 100mm PVC plug | -/120/120 | 1 | FSP2153 |
H100S blanked off with 100mm PVC plug | -/120/120 | 4 | FSP2153 |
H65S blanked off with 65mm PVC plug | -/120/120 | 2 | FSP2153 |
H50S blanked off with 50mm PVC plug | -/120/120 | 3 | FSP2153 |
Unique Elements | |||
Details | FRL | Specimen # | Report No. |
Permanent Metal Deck Slabs | |||
Cast-in collars systems on Bondeck | -/120/120 | Section 3.3, a. | FCO3426 |
Cast-in collars systems on other steel permanent formwork | -/120/120 | Section 3.3, a. | FCO3426 |
MgO Board Walls | |||
FireCrunch wall systems with SNAP retrofit collars | -/90/90 | FCO3268 | |
Multiboard wall systems with SNAP retrofit collars | -/90/90 | FCO3369 | |
Plasterboard Ceiling | |||
100mm PVC stack through a LP100R-D on a plasterboard ceiling | -/90/90 RSIF 60min | 2 | FSP2097 |
100mm PVC floorwaste through a LP100R-D on a plasterboard ceiling | -/90/90 RSIF 60min | 1 | FSP2097 |
50mm PVC floorwaste through a LP50R on a plasterboard ceiling | -/90/90 RSIF 60min | 3 | FSP2097 |
110mm Raupiano stack through a LP100R-D on a plasterboard ceiling | -/90/90 RSIF 60min | 1 | FSP1906 |
110mm Raupiano floorwaste through a LP100R-D on a plasterboard ceiling | -/90/90 RSIF 60min | 2 | FSP1906 |
50mm Raupiano stack through a LP50R on a plasterboard ceiling | -/90/90 RSIF 60min | 3 | FSP1906 |
20mm PEX-a stack through a 32R on a plasterboard ceiling | -/90/90 RSIF 60min | 4 | FSP2097 |
Shaft Liner Walls | |||
Range of SNAP retrofit collars covering various pipe materials | -/120/120 | FCO3348 |
† Refer to report in conjunction with FCO3407
†† Refer to report in conjunction with FC14077